What a journey this has been. It all started with our participation in the tender, where we spent many hours interpreting the requirements and figuring out the trailer generator.

The excitement reached its peak when we were awaiting the award until the redeeming news: we were awarded the contract to build and supply the 150kVA Netzersatzanlagen to the Polizei!

After this great moment, it was immediately time to get to work. We started with construction discussions and further development of the product. A Volvo engine combined with a Mecc Alte generator, with the control being done by a Deep Sea module.

During the construction phase, we ran into some challenges, but thanks to the expertise of our experienced mechanics and engineers, these were quickly remedied.

The result was impressive when the Netzersatzanlagen were handed over to the customer at the end of last year. Proud of our team and of the beautiful product we delivered!